New D6 section near Lubenec opens mid-October — a shorter route to the German border

24 Sep 2026

The Road and Motorway Directorate has announced that the first stage of the D6 motorway between Petrohrad and Lubenec will open in mid-October 2026 — nearly a year behind the original December 2025 schedule. Contractors point to unexpected subsoil conditions that differed from the design assumptions. The new section includes a 2.2km bypass around the village of Ležky, and within five to seven weeks of opening, the existing temporary exit onto road I/6 near Lubenec will be removed.

For carriers heading toward Karlovy Vary, Cheb and on into Germany, this is a meaningful improvement — it takes pressure off parallel lower-class roads and should make the route smoother. The second stage, toward Prague, is facing similar geological issues, with completion now expected in 2028 rather than 2027 — so a fully connected D6 is still a way off.